Planning Board Meeting – BESS Application
Summary of March 29, 2023 Planning Board Meeting – BESS Application
MEETING RECAPS
3/29/20231 min read
Project & Request
Applicant: KCE NY 29, LLC (Key Capture Energy)
Location: 220 Rabro Drive, Hauppauge (SE corner of Rabro Drive and Wheeler Road / Route 111)
Project: Tier 3 Battery Energy Storage System (BESS)
The applicant requested:
A Planning Board special permit under Town Code §68-456(F)(3)
A waiver of standard fencing requirements to allow a visual and sound barrier wall
Associated site plan modifications
Key Points Presented to the Planning Board
The BESS facility would interconnect directly with the existing LIPA substation located directly across Rabro Drive.
A decommissioning plan was submitted after the public hearing in response to Planning Board requests.
The plan was prepared by Key Capture Energy and its consultants, H2M Architects and Engineers.
The exact location of the monitoring/control center was unknown at the time of approval.
The monitoring location would be selected during the construction phase.
Monitoring services were stated to be provided by Merit Controls, headquartered in New Jersey.
The applicant asserted that remote monitoring would not affect the ability to dispatch local emergency responders.
Planning Department Recommendation
Planning staff confirmed receipt of the required decommissioning plan.
Staff accepted the applicant’s explanation regarding the unknown monitoring location.
Planning recommended approval subject to conditions, including limiting battery container height to 12 feet and requiring enhanced landscaping along street frontages.
Planning Board Discussion
No questions were raised by Planning Board members.
No discussion occurred on the record regarding fire risk, emergency response planning, or worst-case incident scenarios.
The applicant agreed to all proposed conditions of approval.
Decision
A motion was made and seconded to approve the application.
The vote was unanimous.
The Planning Board granted the special permit for the Tier 3 BESS.
Key Observations
The project was approved despite the monitoring location being undetermined.
The Board relied primarily on applicant representations and Planning staff recommendations.
There was no documented independent expert review or detailed safety discussion.
The approval predates later Town actions increasing scrutiny of BESS projects, including moratoriums.